HOUSES
REHABILITATION OF 51 + 43 INDIVIDUAL DWELLINGS
AVION – Cité d’Arleux (62)
- REHABILITATION
- NEW
- REALIZATION IN OCCUPIED SITE
BUILDING OWNER
MAISONS ET CITES
GROUP
DURATION OF WORKS
Forecast duration of works:
- Firm slice: 13 months
- Optional slice: 18 months
INVESTMENT
- Firm slice: €2,166,000 duty free
- Optional slice: €2,867,000 duty free
SURFACE / TYPE
97 m² / house
PROJECT
58 houses in complete rehabilitation
- Asbestos removal of the houses
- Complete isolation of the houses
- Compliance of electrical installations
- Replacement of exterior joinery
- Renovation of all the surroundings and gardens
- Treatment of all facades
36 Houses in outdoor treatment
- Treatment of all facades
- Treatment of the surroundings
MISSION(S) COMPLETE WORKS MASTERY + OPC
- Complete works mastery mission
- BET Thermical
- BET Fluids
- Economist