REHABILITATION OF 51 + 43 INDIVIDUAL DWELLINGS AVION

HOUSES

REHABILITATION OF 51 + 43 INDIVIDUAL DWELLINGS

AVION – Cité d’Arleux (62)

BUILDING OWNER

MAISONS ET CITES

GROUP
DURATION OF WORKS

Forecast duration of works:

  • Firm slice: 13 months
  • Optional slice: 18 months
INVESTMENT
  • Firm slice: €2,166,000 duty free
  • Optional slice: €2,867,000 duty free
SURFACE / TYPE

97 m² / house

PROJECT

58 houses in complete rehabilitation

  • Asbestos removal of the houses
  • Complete isolation of the houses
  • Compliance of electrical installations
  • Replacement of exterior joinery
  • Renovation of all the surroundings and gardens
  • Treatment of all facades

36 Houses in outdoor treatment

  • Treatment of all facades
  • Treatment of the surroundings
MISSION(S) COMPLETE WORKS MASTERY + OPC
  • Complete works mastery mission
  • BET Thermical
  • BET Fluids
  • Economist